Most reports stop at the total. One number for the whole portfolio, and no cause.
Break it down by site and split each variance three ways:
Usage: the change in volume at the budget rate. Rate: the change in unit price on actual volume. Contract: charges from contract terms, such as volume bands, minimums and fixed fees.
In our illustrative three-site example, Site A used more energy, Site B paid a higher rate, and Site C used less but paid a volume-band charge that took back almost half the saving.
Across the portfolio, usage nets to zero. The whole overrun is rate and contract. A usage-only fix would have missed both.
Variance becomes actionable only when the cause is separated.
NoteIllustrative three-site example. Figures are not a customer result.